Today's work was all about seats. Two days ago chair seats were removed, as you can see in the picture. Yesterday, workers removed the chair backs. But by the end of today's work...
... the auditorium looked like this! The chair legs were the last things to be removed, leaving the auditorium floor completely bare. Portions of aisle carpet were removed as well, as you can see by the black patches.Workers then proceeded to sweep up the bolts that had been left on the floor. Although they're one of the first things to be removed, the new chairs, which will be blue, won't be placed in the auditorium until about september.
Also worked upon today was the stage. The rest of the floorboards were removed, as well as the floor sleepers and the sand, leaving a bare layer of concrete. The fiberglass insulation will be placed in the coming days.